How much extra to bake

The reserve is the extra bread you bake above what you expect to sell. There is no percentage that is right for everyone: choose it by comparing what you lose if a piece is left over (its cost) with what you lose if you run short (the profit of the sale you did not make). The cheaper the piece and the more profit it leaves, the more reserve it deserves.

Updated: 2026-11-27

What each mistake costs

If a piece is left over, you lose what it cost to make: ingredients, gas and labour. If you run short, you lose the profit of that sale and sometimes the customer. For many products running short costs more than a leftover, which is why it pays to leave a margin, but not the same one for every product.

Piece in the exampleFigure
Selling price$20
Cost to make it$7
If it is left over, you lose$7
If you run short, you lose (price minus cost)$13

The steps

  • 1. Work out, per product, the cost of the piece and its profit (price minus cost).
  • 2. Divide the profit by the sum of the profit and the cost. In the example: 13 over 20, that is 65%. That is the share of days on which the product should last: about 6 or 7 days out of 10.
  • 3. Take the product's sales on the last equal days (for example, 8 Fridays) and sort them from lowest to highest.
  • 4. Find the quantity that would have been enough on that share of days. That is the quantity to bake; the reserve is what lies above the average.
  • 5. Check every week with what was left and what ran out, and move the quantity little by little.

An example (invented numbers)

A Friday concha, with the sales of the last 8 Fridays, sorted:

Friday (lowest to highest)Pieces sold
1st62
2nd70
3rd74
4th78
5th81
6th85
7th90
8th98

The average is 80 pieces. To be enough on 65% of the days you must cover up to the 6th Friday: 85 pieces. The reserve is about 5 pieces, 6% above the average. These are invented numbers and 8 days are few: use them as a starting point, not as a rule.

When to raise or lower the reserve

  • Raise it if the product runs out before the afternoon, if it leaves a lot of profit or if what is left over sells the next day at almost the same price.
  • Lower it if the product is often left over, if it is expensive to make or if it cannot be sold the next day.
  • Be careful with products that ran out: the till only records what sold, so a sold-out day shows less demand than there was. Note what ran out and at what time.

How Hornada does it

Hornada forecasts each product and builds the plan in batches with the reserve you choose; you adjust it in the dashboard. At closing you note what was left and what ran out, and with that you see how the chosen reserve is doing. The cost-and-profit calculation per piece is yours to do.

Frequently asked questions

What reserve percentage is normal?

There is no single valid one: it depends on the cost and the profit of each product and on whether what is left over can be sold the next day. The calculation above gives you yours.

Is the reserve the same for every product?

No. It pays more on those that leave more profit and cost less, and less on those that are expensive to make or do not keep until the next day.

How many days of sales do I need?

With 8 equal days there is already a starting point; the more days, the firmer the quantity.